Mauritania
With a cumulative score of 0.91, Mauritania ranks number 99 among emerging markets and number 128 in the global ranking.
- Emerging markets
- Middle East & Africa
1.16 / 5
Power score
0.30 / 5
Transport score
Buildings score
Only 56 markets (28 emerging markets) are scored on the Buildings sector. See the full list on the methodology page.
Low-carbon strategy
Net-zero goal and strategy
Mauritania’s net-zero goal remains under discussion and it does not have a long-term carbon strategy.
Nationally Determined Contributions (NDC)
Mauritania in October 2021 submitted its updated Nationally Determined Contribution (NDC), a non-binding plan to achieve the goals set out in the 2015 Paris Agreement. It has pledged to reduce greenhouse-gas emissions by 11% in 2030 compared with its business-as-usual scenario (BAU), which would avoid more than 1.8 million metric tons of CO2 equivalent. But emissions would still grow under this scenario.
This unconditional target assumes that Mauritania receives the same amount of international support to that received until 2020, or a total of $635 million, according to the government’s estimates. As outlined in its NDC, Mauritania states that it could ensure carbon neutrality and a 92% reduction of its greenhouse gas emissions by 2030 if it receives $33.6 billion more in international support. This additional ambition would avoid more than 16 million tons of CO2 equivalent, per government estimates.
Fossil fuel phase-out policy
There is no fossil-fuel phase-out policy in Mauritania.
Power
Power policy
Mauritania’s government has rolled out little in the way of incentives to deploy clean energy. Since 2013, it has issued three auctions for engineering, procurement, and construction (EPC) contracts to build solar and wind. These auctions led to the construction of the 30-megawatt wind farm outside Nouakchott and the 50-megawatt Toujounine solar PV plant. The latest project, a 100-megawatt wind farm in Boulenoir, is waiting for the state utility Societe Mauritanienne d’Electricite Sna (Somelec) to resolve grid balancing issues to start operations. All grid-connected renewable projects were financed almost entirely by development funds from Arab countries. Siemens Gamesa and Elecnor SA are providing the EPC and maintenance services for both wind farms.
Mauritania has already exceeded its renewable energy target of 20% of total electricity generation by 2020. The power mix is currently at 35-40% of renewable generation, thanks to existing hydro, wind, and solar generation. The official government target is 50% of renewable generation by 2030, which the country should hit once the 100-megawatt wind farm becomes operational. To transition to 100% carbon-free power, the biggest challenge is to replace the country’s thermal generation, which currently runs on diesel and heavy fuel oil, with clean power. The current plan is to retrofit part of the country’s biggest power plant, the North Central thermal station, to run on natural gas instead of diesel or heavy-fuel oil.
The government wants to double the rural electrification rate to 12% by 2024 from 6% in 2022 by expanding the state-led mini grid program and electrifying at least 200 villages. In the long term, the objective is to increase rural electrification rates to 40% and achieve universal access in urban areas by 2030.
Power policies
Power prices and costs
Generous subsidies have kept retail tariffs stable over the past few years. Compared with neighboring countries, Somelec’s power tariffs are low, at an average retail price of $156.41 per megawatt-hour. However, most citizens pay discounted ‘social’ rates bankrolled by the state while rural consumers are faced with steeper bills levied by microgrid operators. There is little regulatory clarity concerning how tariffs are determined and adjusted. The latter falls under the remit of regulatory agency Autorite de Regulation.
Power market
Mauritania’s state utility Somelec owns the generation, grid, and retail electricity sectors. But the government introduced structural reforms in 2022, which would break up Somelec into four different companies and open power generation to competition. The new, independently run Somelec entities would still control the transmission, distribution, and retail sectors. Still, there are no planned auctions or offtake frameworks for independent power producers (IPPs) to build new renewable projects. The government plans to issue specific decrees and frameworks for the terms and duration of new power purchase agreements between IPPs and Somelec.
Most industrials in Mauritania, mainly in the mining sector, have built on-site solar, wind and diesel projects. With the new reforms, industrials would be allowed to sell the excess generation of their on-site projects back into Somelec’s grid. To do so, the company would need to obtain a license that justifies that Somelec benefits from using this excess electricity. Commercial and industrial (C&I) customers are also able to purchase electricity from an on-site project owned and operated by a third party if the project is bigger than 30 kilowatts and there is a bilateral contract in place.
In rural areas, operators with a concession may participate in power generation, distribution, and retail. This license, which the government issues via tenders, allows private companies to build, operate and sell electricity from a mini grid at pre-determined prices. The fixed prices for mini grids are 5 ouguiya ($0.13), 9 ouguiya and 12 ouguiya per kilowatt-hour depending on the project size. As of July 2022, there were 20 new mini grids under construction or up for tender, according to the Ministry of Petroleum, Mines and Energy.
For the financing, the government uses funds from development banks to pay for 90% of the upfront capital expenditure of a mini grid. PV-diesel hybrid projects are the most popular form of rural mini grids, but the government wants to prioritize solar paired with battery storage in its mini-grid expansion efforts. The size of these mini grids can range from 30-200 kilowatts in size, per government estimates, but some can be as large as 2-6 megawatts.
The discovery of offshore gas has made the government eager to begin selling energy to its neighbors and convert some of its thermal generation plants to natural gas from diesel and oil.
Installed Capacity (in MW)
Electricity Generation (in GWh)
Utility privatisation
Which segments of the power sector are open to private participation?
Wholesale power market
Does the country have a wholesale power market?
Doing business and barriers
Mauritania has built out large transmission infrastructure that can accommodate plenty of new large-scale renewable power generation. But power interruptions at the distribution grid level remains a problem for electricity reliability.
Grid balancing issues at interconnection points are one of the biggest barriers to build large-scale renewables. Voltage and frequency spikes at these points force existing renewable projects to shut down three to four times per month during at least a couple of hours. These rapid shutdowns, if they happen too often, can seriously damage a wind or solar plant’s equipment. Mauritania’s grid operator Somelec must prioritize regular maintenance and oversight of the grid, implement grid balancing programs and invest in necessary upgrades. Transparent grid extension plans and clear rules on interconnection would also reduce project development risks.
Physical and demographical challenges also make large-scale renewable development hard. Mauritania is a vast country but its population size of roughly 4 million to 5 million is very geographically dispersed across the country. About 60% of the population lives in cities, and a quarter of households are nomads. Urbanization and population growth should increase electricity demand in dense areas.
The country already has excess grid-connected power capacity, but generation is heavily reliant on a few power plants. Peak electricity demand in Mauritania is just about 200 megawatts, compared with over 450 megawatts of available power capacity, which excludes the new 100-megawatt Boulenoir wind farm.
Even after the upcoming liberalization of power generation, new IPP project development will be limited unless companies can earn very high returns and have access to strong loan guarantees, credit enhancement mechanisms and investor protection rules. Soft costs as well as regulatory and market risks are too high to justify new projects, especially given the small population size of Mauritania, per interviews with international developers. Even if the country were to replace the 312 megawatts of thermal power installed with clean sources, the ambition is too small for most big energy companies with experience in Africa. Somelec, which would purchase all power from new IPP projects, is also heavily indebted and at the brink of bankruptcy.
Currency of PPAs
Are PPAs (eg. corporate PPAs and all other types) signed in or indexed to U.S. Dollars or Euro?
Bilateral power contracts
Can a C&I (Commercial and Industrial) customer sign a long-term contract (PPA) for clean energy?
Fossil fuel price distortions - Subsidies
Does the government influence the wholesale price of fossil fuel (used by thermal power plants) down through subsidies?
Fossil fuel price distortions - Taxes
Does the government influence the wholesale price of fossil fuel (used by thermal power plants) up through taxes or carbon prices?
Transport
EV market
The government has yet to implement any substantive policy support in the transport and electric vehicle sectors.
EV policy
The government has yet to implement any substantive policy support in this sector.
Transport policies
Fuel economy standards
Does the country have a fuel economy standard in place?
Buildings
Buildings market
The government has yet to implement any substantive policy support in the buildings sector.
Energy efficiency policy
Does the country have a national energy efficiency plan?
Energy efficiency policy
Are there minimum energy performance standards for buildings?
Energy efficiency incentives
Is there access to loans or grants for energy efficiency measures (i.e. Wall or loft insulation or double glazing)?
Buildings policy
The government has yet to implement any substantive policy support in this sector.
Buildings policies
Additional insights
from BNEF
Explore more detailed information on global commodity markets and the disruptive technologies driving the transition to a low-carbon economy.



